How long does a construction defects claim take?

There is no fixed duration for a construction defects claim. The time depends mainly on three things: how long the stage before the claim takes, meaning notice to the contractor and the opportunity to repair; whether the court appoints its own expert; and whether the case ends in a settlement or goes on to evidence and appeal.

An example from a Supreme Court judgment of 18.8.2026: the apartments were handed over in March and April 2021, the claim was filed on 16.1.2022, and the case went through the Magistrates' Court, the District Court and the Supreme Court. The decision was given more than four and a half years after the claim was filed.

What happens before the claim is filed?

Before the claim, the contractor is given an opportunity to repair and an engineer's opinion is ordered.

Under section 4B of the Sale (Apartments) Law, 5733-1973, a buyer who discovers a defect must give the contractor a fair opportunity to repair it, and the contractor must repair it within a reasonable time. A claim filed without this stage may end in reduced compensation, as the Supreme Court held in Civil Leave to Appeal 18136-03-26. This stage takes time, but it is part of the road, not a delay.

At this stage an engineer's opinion is also ordered, and the amount of the claim rests on it.

What are the stages of the claim itself?

  1. Filing a statement of claim, with the engineer's opinion.
  2. The contractor's statement of defence, and sometimes a counter-opinion on its behalf.
  3. Pre-trial hearing. In construction defects cases the court often appoints its own expert, who inspects the apartment and submits an opinion.
  4. Clarification questions to the expert, and sometimes cross-examination.
  5. Settlement, or evidence, summations and judgment.
  6. Appeal, if one of the parties files one.

Each stage also depends on the court's schedule, so an end date cannot be promised in advance. On the stages of a civil claim see stages of a civil claim.

What makes the process longer?

  • A dispute over whether the defects exist at all, which requires a court-appointed expert.
  • Several defendants, for example a developer, a building contractor and subcontractors.
  • Defects in the common property, where the claimant is the building's representative committee. See a committee's claim for defects in the common property.
  • Preliminary arguments, such as an arbitration clause in the contract or prescription.
  • An appeal against the judgment.

What can be done to shorten it?

  • Send the contractor written notice early, with a list of defects and photos, and document every repair attempt.
  • Order a detailed engineering opinion, with a cost estimate for each defect.
  • Consider a settlement after the court expert's opinion, when the range is clearer.
  • Check early whether the contract has an arbitration clause.

And what about prescription while the case is running?

As a rule, a claim must be filed within seven years from the day the cause of action arose (sections 5 and 6 of the Prescription Law, 5718-1958). Filing the claim stops the clock, and the length of the proceedings does not harm it. So the important calculation is by when to file, not how long the case will last. Details in the article prescription in construction defects claims.

Case law and sources

About the author

Amos Ilan, Advocate, is a lawyer (Bar No. 35320) and a notary (licence 214444). The office is at 17 Tzahal Street, Nes Ziona, and handles real estate transactions, construction defects, condominium disputes and civil litigation. Alongside his legal work he has practical knowledge, not based on formal training, of engineering, appraisal and electrical and building systems, and he personally conducts the cross-examination of experts in construction defects cases.

Disclaimer. Nothing in this article constitutes legal advice or a substitute for it. Each case is examined on its own facts and documents.

Questions and answers

Does a settlement shorten the case?

Yes. A settlement agreement that the court gives the force of a judgment ends the proceedings at that stage. After the court expert's opinion the parties usually have a clearer picture of the amount, so this is a stage at which settlement is considered.

Can the contractor repair even after a claim has been filed?

The parties can agree on a repair at any stage. Whether the contractor was given a fair opportunity to repair before the claim affects the amount of compensation, as the Supreme Court held in 2026.

What happens if the claim was not filed in time?

A claim filed after the prescription period may be dismissed. So it is worth checking the deadlines early, even while negotiations with the contractor are still going on.

Need a lawyer or a notary?