On the day the apartment was placed at the buyer's disposal, meaning at handover, and not on the day the contract was signed (section 4(c) of the Sale (Apartments) Law).
Inspection period and warranty period: what is the difference?
The inspection period and the warranty period are two periods that section 4 of the Sale (Apartments) Law, 5733-1973 sets for defects in an apartment bought from a contractor. The main difference is who must prove what: during the inspection period the contractor is liable for a defect that appeared, unless it proves the buyer caused it. During the warranty period the buyer must prove that the defect originates in the design, the work or the materials.
The inspection period lasts between one and seven years, depending on the type of defect, and starts on the day the apartment was placed at the buyer's disposal. The warranty period lasts three more years and starts at the end of the inspection period.
What does the law say?
Section 4(a)(2) of the Law provides that the contractor has not met its obligations if a non-conformity appeared in the apartment during the inspection period, unless it proves that the non-conformity was caused by an act or omission of the buyer. Section 4(a)(3) provides that the contractor is liable during the warranty period too, but only if the buyer proves that the non-conformity originates in the design, the work or the materials.
Section 4(c) defines both periods: the inspection period is "a period set out in the Schedule, starting when the apartment is placed at the buyer's disposal", and the warranty period is "a period of three years starting at the end of the inspection period".
How long is the inspection period for each defect?
The Schedule to the Law sets a different inspection period for each type of defect. Each is followed by three years of warranty.
| Type of defect | Inspection period | With the warranty period |
|---|---|---|
| Metalwork and carpentry products, including aluminium and plastic | Two years | Five years |
| Interior flooring and cladding, including subsidence and wear | Two years | Five years |
| Failure in the function and durability of machinery and boilers | Three years | Six years |
| Yard development, including subsidence of paving on the ground floor, in parking, pavements and paths | Three years | Six years |
| Failure in components of the thermal insulation systems | Three years | Six years |
| Failure in piping systems: water, heating, gutters, grey water and sewage, including leaks | Four years | Seven years |
| Failure in the building's waterproofing, including underground spaces, walls, ceilings and roofs | Four years | Seven years |
| Cracks wider than 1.5 mm in non-load-bearing elements | Five years | Eight years |
| Detachment, peeling or crumbling of exterior cladding | Seven years | Ten years |
| Any other non-conformity that is not a fundamental non-conformity | One year | Four years |
For example, a leak from piping is covered by a four-year inspection period from handover, and by the warranty period in the three years that follow. You can work out the dates for your apartment with the inspection and warranty period calculator.
What changes when the inspection period ends?
The contractor remains liable, but the burden of proof moves to the buyer.
During the inspection period it is enough that the defect appeared, and it is the contractor that must prove the buyer caused it, for example through improper use or a renovation. During the warranty period the buyer must show that the defect results from the design, the work or the materials. This is usually done with an engineer's opinion.
What about a defect in the building's structure?
For a fundamental non-conformity, meaning a defect in the parts of the building that carry and transfer loads to the ground and that concerns the building's stability and safety, section 4(a)(4) sets a period of 20 years from the day the apartment was placed at the buyer's disposal. Even after that, the contractor is liable under section 4(a)(5) if the buyer proves that the defect originates in the design, the work or the materials.
By when must the contractor be notified of the defect?
The inspection period is not the notice deadline. Notice is given according to the deadlines in section 4A.
Under section 4A of the Law, a defect that could have been discovered at handover must be notified to the contractor within one year of handover. A defect that could not have been discovered on a reasonable inspection is notified within a reasonable time after it is discovered. After notice, the contractor must be given a fair opportunity to repair, under section 4B. The site has a letter generator for notice to the contractor.
And after both periods have ended?
The end of the warranty period is not necessarily the end of the road. Section 7 of the Law provides that the Law does not detract from the buyer's rights under any other law. In parallel, the prescription period runs, which is a separate question: until when a claim can be filed. See the article prescription in construction defects claims.
Did you buy a second-hand apartment?
The Law also gives these rights to a "subsequent buyer", meaning someone who bought the apartment from the first buyer. The periods do not start again: they are counted from the day the apartment was placed at the first buyer's disposal. Details in the article construction defects in a second-hand apartment.
Which apartments do these periods apply to?
The periods in the table were set by Amendment No. 5 to the Law. Under section 11(c), the amendment does not apply to an apartment whose sale contract was made, or whose building was completed, before 6.4.2011. The previous version of the Law applies to such apartments.
Case law and sources
- The Sale (Apartments) Law, 5733-1973: sections 4, 4A, 4B, 7, 7A, 11 and the Schedule.
About the author
Amos Ilan, Advocate, is a lawyer (Bar No. 35320) and a notary (licence 214444). The office is at 17 Tzahal Street, Nes Ziona, and handles real estate transactions, construction defects, condominium disputes and civil litigation. Alongside his legal work he has practical knowledge, not based on formal training, of engineering, appraisal and electrical and building systems, and he personally conducts the cross-examination of experts in construction defects cases.
Questions and answers
When does the inspection period start?
The inspection period is over. Is the contractor still liable?
Yes. During the three years of the warranty period that follow, the contractor is still liable, but the buyer must prove that the defect originates in the design, the work or the materials.
Can the contract shorten the periods?
No. Under section 7A of the Sale (Apartments) Law, the Law cannot be contracted out of except in the buyer's favour. A contract clause that shortens the inspection or warranty periods will not bind the buyer.
What is the difference between the inspection period and prescription?
The inspection period determines which defects the contractor is liable for and who must prove what. Prescription determines until when a claim can be filed. These are two separate clocks.