No. It shows the position on the data entered: in which period the defect was discovered, whether notice was given in time, and the next step. Whether there is a claim, and for how much, also depends on an engineering opinion and the documents.
Construction Defects Check: Is the Contractor Liable and What Now
Answer a few questions about the apartment, each defect (you can add several) and what has been done, and get an overview: whether the defect falls in the inspection or warranty period under the Sale (Apartments) Law, whether notice was given in time, the rule when the contractor does not repair, an estimate of the limitation date, which documents are missing, and the next step.
Disclaimer: the result is general information based on the data entered and is not legal advice or an engineering opinion. Do not make a decision on the basis of the result alone. Use of the check is at the user's responsibility and subject to the terms of use and disclaimer.
What does the check examine?
Five things, in the order they matter in a construction defects case: whether the contractor is liable, whether notice was given in time, whether the contractor had an opportunity to repair, how long is left before limitation, and which documents to collect before going further.
When is the contractor liable for a defect?
During the inspection period the contractor is liable for any non-conformity discovered, unless they prove the buyer caused it. During the warranty period, the three years after the inspection period, they are liable if the buyer proves the defect originates in the design, workmanship or materials (section 4 of the Sale (Apartments) Law).
The inspection period depends on the type of defect in the Schedule to the Law: from one to seven years. A fundamental non-conformity in the load-bearing parts of the building has an inspection period of 20 years. And an apartment that differs from the specification, an official standard or the building regulations is a non-conformity regardless of the periods.
By when must you notify the contractor?
For a defect that a reasonable inspection at delivery could have found, within one year of delivery. For a hidden defect, within a reasonable time after it was discovered (section 4A). Notice should be in writing, with a description of the defect and the date of discovery.
What if the contractor does not repair?
The buyer must give the contractor a proper opportunity to repair, and the contractor must repair within a reasonable time. If the defect returns after a repair within two years of the notice, or the repair is urgent and the contractor did not repair within a reasonable time, the buyer may repair it and the contractor bears the cost (section 4B).
And limitation?
A claim generally becomes time-barred seven years after the cause of action arose, and in a non-conformity claim against an apartment seller the starting point is delivery (sections 5 and 6 of the Prescription Law). For a hidden defect you may argue that time began on discovery (section 8). A notice to the contractor does not stop the clock. More in limitation in construction defects claims.
Does the check work for a second-hand apartment?
Yes, if you bought from the first buyer of a new apartment: you are a "subsequent buyer", and the periods run from delivery to the first buyer. If you bought from someone who did not build the apartment, the inspection periods of the Sale (Apartments) Law do not apply, and the check explains what applies instead. In a self-build they apply only if the contract with the contractor says so, and the check asks whether it has such a clause.
How the check calculates: the formula, the assumptions and a worked example
The formula. End of inspection period = delivery date + the inspection period for the type of defect under the Schedule to the Sale (Apartments) Law. End of warranty period = end of inspection + three years. If the discovery date is no later than the end of inspection: within inspection; if no later than the end of warranty: within warranty. Deadline to notify of a visible defect = one year from delivery. Limitation estimate = delivery date + seven years, plus the days from 7 October 2023 to 6 April 2024 if the period had not ended by 25 January 2024 (section 15A of the Prescription Law). A period ends on the day with the same number as the delivery day (section 10(b) of the Interpretation Law).
The assumptions. The applicable version follows the contract date and the construction completion date: Amendment 5 for contracts and buildings from 6 April 2011, and before that Amendment 3 of 1990 (section 11). Classifying the defect under the Schedule is a professional question, decided by an engineer's opinion if disputed. A "reasonable time" to notify of a hidden defect is not a fixed number of days; the court examines it on the facts. The limitation estimate ignores any other suspension or extension.
Worked example. An apartment was delivered on 15 March 2022 under a 2020 contract. On 10 January 2026 damp was found in a wall, not visible at delivery, and no notice has been sent yet. Damp and waterproofing: an inspection period of four years, to 15 March 2026, then warranty to 15 March 2029. The defect was discovered within the inspection period, so the contractor is liable unless they prove the buyer caused it. As it is a hidden defect, notice is due within a reasonable time from 10 January 2026. Limitation estimate: 15 March 2022 + 7 years = 15 March 2029, plus 183 days of the war period, that is by 14 September 2029.
The source. Sale (Apartments) Law, 1973, sections 4, 4A, 4B, 11 and the Schedule; Prescription Law, 1958, sections 5, 6, 8 and 15A; Interpretation Law, 1981, section 10(b); CA 830/06 Gelman v. Cohen Development-Daraad (2 April 2008). Updated: 24 November 2026.
Questions and answers
Does the check decide whether I have a claim?
What is the difference between the inspection and warranty periods?
During the inspection period the contractor is liable unless they prove the buyer caused the defect. During the warranty period, the three years after it, the buyer must prove the defect originates in the design, workmanship or materials.
How soon must I notify the contractor?
For a defect that could have been found at delivery, within one year of delivery. For a hidden defect, within a reasonable time of discovery. Give written notice as soon as the defect is found.
When may I repair it myself at the contractor's expense?
When the defect returned after the contractor repaired it, within two years of the notice, or when the repair is urgent and the contractor did not repair within a reasonable time (section 4B(b), for contracts under the 2011 version).
Is the data I enter sent to the office?
No. The check runs in your browser. Data is sent only if you choose to receive the report by email.